✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
# |
dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||||
1 | 12/2013 | D1 | 14,9 km | 4 | 3 | 341 mil. € | 21 683 | 12 491 - 24 900 | 1 | 1 | |||||||||
2 | 6/2014 | D1 | 13,5 km | 4 | 1 | 555 mil. € | 28 353 | 22 691 - 32 334 | 1 | 2 | |||||||||
3 | 7/2019 | R4 | 4,3 km | 4 | 1 | 179 mil. € | 15 022 | 15 837 - 18 098 | 1 | 3 | 17,5 | 5/2004 | |||||||
4 | 8/2019 | R2 | 13,5 km | 4 | 1 | 142 mil. € | 11 490 | 9 007 - 9 998 | 2 | 2 | 16,0 | 11/2004 | |||||||
5 | 3/2020 | R2 | 9,1 km | 4 | 1 | 267 mil. € | 12 064 | 8 780 - 11 203 | 3 | 4 | 16,0 | 11/2004 | |||||||
6 | 3/2021 | R3 | 4,4 km | 2 | 2 | 70 mil. € | 7 754 | 10 334 - 11 542 | 2 | 2 | 27,0 | 8/2006 | |||||||
7 | 1. | 10/2021 | R4 | 14,3 km | 4 | 3 | 202 mil. € | 15 320 | 10 088 - 50 895 | 2 | 1 | 14,4 | 6/2014 | ||||||
8 | 3. | 3/2022 | D1 | 3,5 km | 8 | 1 | 149 mil. € | 94 554 | 62 652 | . . . | 1 | 1 | 13,8 | 12/2009 | |||||
9 | 4. | 9/2022 | R4 | 10,2 km | 4 | 1 | 299 mil. € | 12 070 | 22 341 - 30 731 | 1 | 3 | 20,4 | 5/2004 | ||||||
87,8 km |
2 - 8 |
14 |
2 205 mil. € |
8 780 - 62 652 | 1,6 |
2,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku