plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
30 úsekov |
318,2 km |
2 - 8 |
7 636 mil. € |
2,8 |
3,1 |
|||||||
1 | D1 | 13,5 km | 4 | Turany 2, Hubová | 1 235 mil. € | 1 | 1 | |||||
2 | R7 | 9,4 km | 4 | Holice s I/63, D. Streda s III/06325 | 191 mil. € | 4 | 5 | |||||
3 | R7 | 23,5 km | 2 | Zemné | 227 mil. € | 4 | 4 | |||||
4 | R7 | 14,3 km | 2 | Nové Zámky | 172 mil. € | 4 | 4 | |||||
5 | R7 | 8,4 km | 4 | Mliečany s II/507, Dolný Bar | 161 mil. € | 4 | 5 | |||||
6 | R2 | 14,1 km | 2 | Rožňava, Jablonov nad Turňou | 272 mil. € | 3 | 2 | |||||
7 | R3 | 4,9 km | 2 | Dlhá nad Oravou | 77 mil. € | 2 | 2 | |||||
8 | R3 | 8,3 km | 2 | Podbiel | 199 mil. € | 2 | 3 | |||||
9 | R2 | 16,0 km | 4 | Trenčianske Mitice | 277 mil. € | 2 | 2 | |||||
10 | R2 | 2,7 km | 4 | 59 mil. € | 3 | 4 | ||||||
11 | R2 | 6,1 km | 4 | Trenčín juh, Trenčianska Turná | 143 mil. € | 3 | 4 | |||||
12 | D3 | 10,8 km | 4 | Krásno nad Kysucou | 309 mil. € | 2 | 4 | 7/2022 | ||||
13 | R2 | 20,7 km | 2 | 211 mil. € | 4 | 4 | ||||||
14 | D3 | 11,2 km | 4 | Brodno, Kysucké Nové Mesto | 410 mil. € | 1 | 1 | 5/2022 | ||||
15 | R4 | 4,0 km | 4 | Lipníky | 105 mil. € | 2 | 2 | |||||
16 | R2 | 10,6 km | 2 | Rimavská Sobota | 125 mil. € | 4 | 4 | |||||
17 | R1 | 4,6 km | 4 | križovatka D1 | 100 mil. € | 4 | 3 | |||||
18 | D3 | 4,0 km | 4 | 179 mil. € | 1 | 2 | ||||||
19 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | ||||||
20 | R2 | 18,0 km | 2 | Moldava nad Bodvou, Šaca | 224 mil. € | 3 | 5 | |||||
21 | D1 | 10,6 km | 8 | Senec | 234 mil. € | 2 | 1 | |||||
22 | R4 | 6,5 km | 2 | Kuková | 116 mil. € | 2 | 3 | |||||
23 | R4 | 7,0 km | 2 | Okrúhle | 122 mil. € | 2 | 2 | |||||
24 | R1 | 14,9 km | 4 | Slovenská Ľupča, Korytnica | 785 mil. € | 3 | 3 | |||||
25 | R2 | 7,8 km | 2 | Jablonov n.Turňou | 73 mil. € | 5 | 4 | |||||
26 | D1 | 19,9 km | 6 | Zeleneč nová, Trnava rekonštrukcia | 321 mil. € | 3 | 2 | |||||
27 | R2 | 9,6 km | 2 | Nováky - západ | 112 mil. € | 2 | 4 | |||||
28 | R2 | 11,5 km | 2 | 235 mil. € | 2 | 4 | ||||||
29 | R4 | 7,9 km | 2 | Hunkovce, Vyšný Komárnik | 129 mil. € | 4 | 3 | |||||
30 | R3 | 5,0 km | 2 | Šahy | 63 mil. € | 3 | 2 | |||||
30 úsekov |
318,2 km |
2 - 8 |
7 636 mil. € |
2,8 |
3,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku