dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
30 úsekov |
318,2 km |
2 - 8 |
68 057 m |
7 636 mil. € |
2 552 - 62 652 | 2,8 |
3,1 |
||||||||||
1 | 7. | 2/2024 | D1 | 13,5 km | 4 | D 26,5/100 | 1 330 m | 1 235 mil. € | 13 676 - 21 949 | 1 | 1 | dopravné, TEN-T | |||||
2 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | 377 m | 191 mil. € | 6 428 - 9 084 | 4 | 5 | ostatné | |||||
3 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | 2 006 m | 227 mil. € | 4 | 4 | ostatné | ||||||
4 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | 2 006 m | 172 mil. € | 4 | 4 | ostatné | ||||||
5 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | 420 m | 161 mil. € | 6 403 - 9 478 | 4 | 5 | ostatné | |||||
6 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 095 m | 272 mil. € | 5 792 - 7 064 | 3 | 2 | ostatné | |||||
7 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R 24,5/80, plánované v 1/2-profile | 1 544 m | 77 mil. € | 2 | 2 | ostatné | ||||||
8 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R 24,5/80, plánované v 1/2-profile | 2 956 m | 199 mil. € | 5 550 - 9 787 | 2 | 3 | ostatné | |||||
9 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R 24,5/120(100) | 1 929 m | 277 mil. € | 9 654 - 12 079 | 2 | 2 | ostatné | |||||
10 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 206 m | 59 mil. € | 12 862 | 3 | 4 | ostatné | |||||
11 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | 1 640 m | 143 mil. € | 12 157 | 3 | 4 | ostatné | |||||
12 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | 2 060 m | 309 mil. € | 14 176 - 14 186 | 2 | 4 | dopravné, TEN-T | |||||
13 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 3 480 m | 211 mil. € | 6 969 - 10 726 | 4 | 4 | ostatné | |||||
14 | 27. | 5/2026 | D3 | 11,2 km | 4 | D 24,5/80 | 3 896 m | 410 mil. € | 13 886 - 21 743 | 1 | 1 | dopravné, TEN-T | |||||
15 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | R 24,5/100 | 2 045 m | 105 mil. € | 14 625 | 2 | 2 | dopravné | |||||
16 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | 1 295 m | 125 mil. € | 6 412 - 8 112 | 4 | 4 | ostatné | |||||
17 | 30. | 10/2026 | R1 | 4,6 km | 4 | R 24,5/80 | 2 982 m | 100 mil. € | 11 611 | 4 | 3 | variant TEN-T | |||||
18 | 31. | 11/2026 | D3 | 4,0 km | 4 | D 24,5/80 | 624 m | 179 mil. € | 15 053 | 1 | 2 | dopravné, TEN-T | |||||
19 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 3 | 4 | ostatné | |||||||
20 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 16 837 m | 224 mil. € | 10 140 - 11 010 | 3 | 5 | ostatné | |||||
21 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | D 41/120 | 359 m | 234 mil. € | 62 652 | . . . | 2 | 1 | dopravné, TEN-T | ||||
22 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | R 24,5/100, plánované v 1/2-profile | 2 205 m | 116 mil. € | 6 651 - 9 113 | 2 | 3 | ostatné | |||||
23 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 1 948 m | 122 mil. € | 3 407 - 3 769 | 2 | 2 | ostatné | |||||
24 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | R 24,5/80 | 4 532 m | 785 mil. € | 8 140 - 13 204 | 3 | 3 | variant TEN-T | |||||
25 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 397 m | 73 mil. € | 5 587 | 5 | 4 | ostatné | |||||
26 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | D 33,5/120 | 321 mil. € | 42 774 - 54 519 | . . . | 3 | 2 | dopravné, TEN-T | |||||
27 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 1 606 m | 112 mil. € | 8 634 - 11 116 | 2 | 4 | ostatné | |||||
28 | 41. | 9/2028 | R2 | 11,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 2 763 m | 235 mil. € | 7 793 | 2 | 4 | ostatné | |||||
29 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | R 24,5/100, plánované v 1/2-profile | 4 710 m | 129 mil. € | 2 552 - 2 737 | 4 | 3 | ostatné | |||||
30 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 809 m | 63 mil. € | 9 492 - 10 279 | 3 | 2 | TEN-T | |||||
30 úsekov |
318,2 km |
2 - 8 |
68 057 m |
7 636 mil. € |
2 552 - 62 652 | 2,8 |
3,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku