dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
odhad INEKO
| ||||||||
45 úsekov |
472,0 km |
2 - 8 |
10 766 mil. € |
2,4 |
2,7 |
5/2017 - 2/2024 |
5/2017 - 10/2021 | ||||||||
1 | 10/2013 | D3 | 12,3 km | 2 | 377 mil. € | 194 - 270 | 2 | 2 | 6/2017 | 6/2017 | |||||
2 | 12/2013 | D1 | 14,9 km | 4 | D 26,5/100 | 341 mil. € | 926 - 1 852 | 1 | 1 | 12/2023 | |||||
3 | 1/2014 | D1 | 11,3 km | 4 | D 26,5/100 | 517 mil. € | 1 675 - 2 070 | 2 | 3 | 1/2021 (0,0) | |||||
4 | 6/2014 | D1 | 13,5 km | 4 | D 26,5/100 | 555 mil. € | 1 254 - 2 069 | 1 | 2 | 2/2024 | |||||
5 | 6/2014 | D3 | 4,3 km | 4 | D 24,5/80 | 269 mil. € | 1 886 - 2 202 | 4 | 2 | 12/2017 | 12/2017 | ||||
6 | 8/2014 | R2 | 7,9 km | 4 | 88 mil. € | 818 - 1 092 | 1 | 1 | 5/2017 | 5/2017 | |||||
7 | 7/2016 | R7 | 17,4 km | 4 | R 24,5/120 | 609 - 806 | 2 | 3 | 7/2020 (0,0) | ||||||
8 | 7/2016 | D4 | 4,4 km | 4 - 6 | D 33,5/120, D 26,5/120 | 1 | 2 | 11/2021 | |||||||
9 | 7/2016 | D4 | 22,6 km | 4 - 6 | D 33,5/120, D 26,5/120 | 1 679 - 8 658 | 1 | 2 | 11/2021 | ||||||
10 | 7/2016 | R7 | 8,4 km | 4 | R 31,5/120 | 676 - 881 | 1 | 1 | 7/2020 (0,0) | ||||||
11 | 7/2016 | R7 | 6,4 km | 4 - 6 | R 31,5/120 | 1 073 - 2 257 | 1 | 1 | 10/2021 | ||||||
12 | 11/2016 | D1 | 14,4 km | 4 | D 26,5/120 | 241 mil. € | 191 - 682 | 2 | 2 | 12/2019 (0,0) | |||||
13 | 12/2016 | D3 | 5,7 km | 4 | D 24,5/80 | 269 mil. € | 741 - 995 | 1 | 2 | 12/2020 (0,0) | |||||
14 | 6/2017 | D1 | 7,9 km | 4 | D 26,5/100 | 434 mil. € | 1 228 - 1 350 | 1 | 2 | 10/2021 | |||||
15 | 12/2017 | D1 | 2,6 km | 4 | R 22,5/80 | 39 mil. € | 800 | 1 | 1 | 1/2021 (0,0) | |||||
16 | 7. | 2/2024 | D1 | 13,5 km | 4 | D 26,5/100 | 1 235 mil. € | 869 - 1 422 | 1 | 1 | |||||
17 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | 191 mil. € | 500 - 623 | 4 | 5 | |||||
18 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | R 11,5/120 | 227 mil. € | 4 | 4 | ||||||
19 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | R 11,5/120 | 172 mil. € | 4 | 4 | ||||||
20 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | R 24,5/120 | 161 mil. € | 451 - 513 | 4 | 5 | |||||
21 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | 272 mil. € | 461 - 521 | 3 | 2 | |||||
22 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R 24,5/80, plánované v 1/2-profile | 77 mil. € | 2 | 2 | ||||||
23 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R 24,5/80, plánované v 1/2-profile | 199 mil. € | 497 - 699 | 2 | 3 | |||||
24 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R 24,5/120(100) | 277 mil. € | 692 - 940 | 2 | 2 | |||||
25 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 59 mil. € | 894 | 3 | 4 | |||||
26 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | 143 mil. € | 1 004 | 3 | 4 | |||||
27 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | 309 mil. € | 875 - 929 | 2 | 4 | |||||
28 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 557 - 946 | 4 | 4 | |||||
29 | 27. | 5/2026 | D3 | 11,2 km | 4 | D 24,5/80 | 410 mil. € | 738 - 1 705 | 1 | 1 | |||||
30 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | R 24,5/100 | 105 mil. € | 888 | 2 | 2 | |||||
31 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | 125 mil. € | 516 - 606 | 4 | 4 | |||||
32 | 30. | 10/2026 | R1 | 4,6 km | 4 | R 24,5/80 | 100 mil. € | 623 | 4 | 3 | |||||
33 | 31. | 11/2026 | D3 | 4,0 km | 4 | D 24,5/80 | 179 mil. € | 1 018 | 1 | 2 | |||||
34 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 3 | 4 | ||||||
35 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 224 mil. € | 570 - 674 | 3 | 5 | |||||
36 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | D 41/120 | 234 mil. € | 4 281 | 2 | 1 | |||||
37 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | R 24,5/100, plánované v 1/2-profile | 116 mil. € | 383 - 425 | 2 | 3 | |||||
38 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 122 mil. € | 201 - 240 | 2 | 2 | |||||
39 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | R 24,5/80 | 785 mil. € | 575 - 1 052 | 3 | 3 | |||||
40 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 73 mil. € | 488 | 5 | 4 | |||||
41 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | D 33,5/120 | 321 mil. € | 2 765 - 3 271 | 3 | 2 | |||||
42 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 112 mil. € | 635 - 690 | 2 | 4 | |||||
43 | 41. | 9/2028 | R2 | 11,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 235 mil. € | 655 | 2 | 4 | |||||
44 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | R 24,5/100, plánované v 1/2-profile | 129 mil. € | 177 - 189 | 4 | 3 | |||||
45 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 63 mil. € | 332 - 531 | 3 | 2 | |||||
45 úsekov |
472,0 km |
2 - 8 |
10 766 mil. € |
2,4 |
2,7 |
5/2017 - 2/2024 |
5/2017 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku