dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
283,8 km |
2 - 6 |
5 698 mil. € |
3,6 |
3,3 |
||||||||||
1 | 46. | 3/2029 | D1 | 7,3 km | 4 | 26,5/100 | 321 mil. € | 3 | 3 | 4/2028 | ||||
2 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | D 26,5/120
(100) | Dargov | 418 mil. € | 3 | 3 | 6/2032 | |||
3 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5 | 5 | |||||
4 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 3 | 4 | |||||
5 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | D 26,5/120
(100) | Hriadky, Pozdišovce | 192 mil. € | 2 | 2 | 6/2032 | |||
6 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | R 11,5/80 (60) | Valaská Dubová, Likavka | 94 mil. € | 4 | 2 | 9/2030 | |||
7 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | R 24,5/80 | Liptovská Osada | 406 mil. € | 4 | 4 | 7/2030 | |||
8 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | R 24,5/100, plánované v 1/2-profile | Kuková | 133 mil. € | 4 | 3 | 2/2029 | |||
9 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | R 24,5/80 | 339 mil. € | 4 | 4 | 7/2030 | ||||
10 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | D 33,5/120 | Stupava | 90 mil. € | 5 | 5 | 9/2031 | |||
11 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | R 24,5/120 (100) | Martin, Rakovo | 191 mil. € | 3 | 3 | 8/2030 | |||
12 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | R 11,5/100 (80) | Púchov západ,
Púchov východ,
Dolné Kočkovce | 182 mil. € | 4 | 3 | 9/2029 | |||
13 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | D 26,5/120
(100) | Sobrance | 139 mil. € | 4 | 3 | 6/2032 | |||
14 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | R 24,5/100 | 1 020 mil. € | 3 | 5 | 7/2030 | ||||
15 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | R 11,5/80 (60) | Široká, Jasenová, v mestskom variante tiež Kocmáľ (Mokraď) a Dolný Kubín stred | 129 mil. € | 3 | 2 | 9/2030 | |||
16 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | D 26,5/120
(100) | Michalovce | 162 mil. € | 3 | 3 | 6/2032 | |||
17 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | R 24,5/100, plánované v 1/2-profile | Giraltovce | 124 mil. € | 3 | 3 | 2/2029 | |||
18 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | D 26,5/120
(100) | Záhor | 136 mil. € | 4 | 3 | 6/2032 | |||
19 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | D 33,5/120 | Stupava | 107 mil. € | 5 | 5 | 9/2031 | |||
20 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | R 24,5/100, plánované v 1/2-profile | Stročín | 101 mil. € | 4 | 3 | 2/2029 | |||
21 | 59. | 7/2031 | R2 | 17,5 km | 4 | R 24,5/100 | Rákoš, Zvolenská Slatina | 287 mil. € | 2 | 2 | 8/2030 | |||
22 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | R 11,5/100 (80) | Mestečko | 222 mil. € | 4 | 3 | 9/2029 | |||
283,8 km |
2 - 6 |
5 698 mil. € |
3,6 |
3,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku