dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
2021 vs 2017)
|
pôvodný zmluvný termín
| ||||||||||
1 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 70 | |||||||
2 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | Stupava | 90 mil. € | 32 968 | . . . | 5 | 5 | 62 | 5,6 | ||||
3 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | Stupava | 107 mil. € | 5 | 5 | 61 | 6,0 | ||||||
4 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | Dargov | 418 mil. € | 9 503 - 9 802 | 3 | 3 | 65 | 7,9 | |||||
5 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | Hriadky, Pozdišovce | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 63 | 7,9 | |||||
6 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | Sobrance | 139 mil. € | 4 033 - 8 369 | 4 | 3 | 66 | 7,7 | |||||
7 | 64. - 68. | 8/2033 | D1 | 12,1 km | 4 | Michalovce | 162 mil. € | 10 444 - 14 783 | 3 | 3 | 64 | 7,7 | |||||
8 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | Záhor | 136 mil. € | 1 698 - 6 812 | 4 | 3 | 67 | 7,7 | |||||
9 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | Sklené,
Ráztočno | 305 mil. € | 3 | 3 | 68 | 5,9 | ||||||
10 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | Prievidza, Brusno, Handlová, Nová Lehota | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 69 | 5,9 | |||||
207,4 km |
2 - 6 |
3 231 mil. € |
1 698 - 32 968 | 3,6 |
3,6 |
61 - 70 |
5.5972602739726 - 7.93972602739726 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku