dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||||
20 úsekov |
269,3 km |
2 - 4 |
5 991 m |
3 921 mil. € |
5 189 - 50 895 | 3,2 |
3,5 |
6 - 69 |
11/2022 - 8/2037 |
|||||||||
1 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 68 m | 105 mil. € | 5 304 | 2 | 2 | 8 | 3/2026 | ostatné | |||||
2 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 449 m | 112 mil. € | 8 634 - 11 116 | 2 | 4 | 40 | 3/2031 | ostatné | |||||
3 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 48 | 9/2032 | ostatné | ||||||
4 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 5 | 4 | 38 | 2/2031 | ostatné | ||||||
5 | 6. | 7/2023 | R2 | 6,8 km | 4 | 1 169 m | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 6 | 7/2026 | ||||||
6 | 3/2020 | R2 | 9,1 km | 4 | 212 m | 267 mil. € | 8 780 - 11 203 | 3 | 4 | 3/2024 | ||||||||
7 | 24. | 12/2025 | R2 | 6,1 km | 4 | 178 m | 143 mil. € | 12 157 | 3 | 4 | 24 | 12/2028 | ostatné | |||||
8 | 26. | 4/2026 | R2 | 20,7 km | 2 | 886 m | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 26 | 4/2028 | ostatné | |||||
9 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 496 m | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 22 | 10/2028 | ostatné | |||||
10 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 1 015 m | 224 mil. € | 10 140 - 11 010 | 3 | 5 | 33 | 12/2029 | ostatné | |||||
11 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 9 007 - 9 998 | 2 | 2 | 11/2022 | |||||||||
12 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 295 m | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 69 | 8/2037 | variant TEN-T | |||||
13 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 253 m | 125 mil. € | 6 412 - 8 112 | 4 | 4 | 29 | 8/2028 | ostatné | |||||
14 | 41. | 9/2028 | R2 | 11,5 km | 2 | 214 m | 235 mil. € | 7 793 | 2 | 4 | 41 | 9/2031 | ostatné | |||||
15 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 60 m | 272 mil. € | 5 792 - 7 064 | 3 | 2 | 17 | 12/2029 | ostatné | |||||
16 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 226 m | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 44 | 2/2032 | ostatné | |||||
17 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 61 m | 59 mil. € | 12 862 | 3 | 4 | 23 | 10/2028 | ostatné | |||||
18 | 47. | 7/2029 | R2 | 14,0 km | 2 | 123 m | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 47 | 7/2032 | ostatné | |||||
19 | 13. | 8/2024 | R2 | 8,3 km | 2 | 57 m | 169 mil. € | 5 277 - 6 250 | 2 | 2 | 13 | 8/2026 | ostatné | |||||
20 | 59. | 7/2031 | R2 | 17,5 km | 4 | 228 m | 287 mil. € | 12 819 - 29 988 | 2 | 2 | 58 | 7/2034 | ||||||
20 úsekov |
269,3 km |
2 - 4 |
5 991 m |
3 921 mil. € |
5 189 - 50 895 | 3,2 |
3,5 |
6 - 69 |
11/2022 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku