dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | 173 mil. € | 12 387 - 17 316 | 10 837 - 15 165 | 2 | 3 | 4/2010 | 4/2026 (+3,7) | ||||||
2 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 7 784 | 6 307 | 4 | 4 | 4/2010 | 5/2033 (+10,2) | ||||||
3 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 9 704 - 13 715 | 8 096 - 11 348 | 4 | 4 | 4/2010 | 5/2033 (+10,2) | ||||||
4 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 7 234 | 6 176 | 4 | 3 | 4/2008 | 7/2033 (+4,3) | ||||||
5 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | 631 mil. € | 5 713 - 13 545 | 4 600 - 11 235 | 5 | 5 | po 2040 | |||||||
6 | 11. | 6/2024 | R1 | 2,7 km | 4 | 155 mil. € | 16 268 | 13 507 | 4 | 3 | 4/2010 | 6/2026 (+3,5) | ||||||
7 | 30. | 10/2026 | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 9 922 | 4 | 3 | 4/2010 | 10/2028 (+3,5) | ||||||
8 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 785 mil. € | 8 140 - 13 204 | 6 735 - 10 692 | 3 | 3 | 4/2010 | 2/2031 (+6,9) | ||||||
9 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 1 988 - 4 251 | 4 | 3 | 4/2008 | 7/2033 (+4,3) | ||||||
9 úsekov |
116,0 km |
2 - 4 |
2 991 mil. € |
2 561 - 17 316 | 3,8 |
3,4 |
4/2026 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku