dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 24. | 12/2025 | R2 | 6,1 km | 4 | 143 mil. € | 2 815 | 3 | 4 | 3/2011 | |||||
2 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 2 829 | 3 | 4 | 3/2011 | |||||
3 | 19. | 6/2025 | R4 | 8,2 km | 2 | 94 mil. € | 1 697 | 3 | 3 | 9/2006 | |||||
4 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 1 279 - 1 930 | 2 | 3 | 12/2009 | |||||
5 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 1 881 - 2 213 | 1 | 3 | 2/2015 | ||||||
6 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 9/2009 | ||||||
7 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | Humienec 330 m | 277 mil. € | 2 269 - 3 025 | 2 | 2 | 7/2010 | ||||
8 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 2 305 - 2 416 | 2 | 2 | 7/2010 | ||||||
9 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 6/2013 | ||||||
9 úsekov |
65,0 km |
2 - 4 |
1 181 mil. € |
2,2 |
2,7 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku