dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||||
1 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 15,1 | 6/2033 (+3,3) | |||||||
2 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 10,8 km | 14 176 - 14 186 | 2 654 - 3 209 | 2 | 4 | 25,0 | 1/2029 (+3,0) | ||||
3 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 105 mil. € | 3,8 km | 14 625 | 1 651 | 2 | 2 | 18,2 | 8/2029 (+3,8) | ||||
4 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | 20,8 km | 6 969 - 10 726 | 1 217 - 1 494 | 4 | 4 | 17,8 | 4/2028 (+4,8) | ||||
5 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 224 mil. € | 16,4 km | 10 140 - 11 010 | 1 245 - 1 287 | 3 | 5 | 14,3 | 12/2029 (+2,8) | ||||
6 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 4,0 km | 15 053 | 3 812 | 1 | 2 | 25,0 | 11/2030 (+6,4) | ||||
7 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 125 mil. € | 9,8 km | 6 412 - 8 112 | 966 - 1 184 | 4 | 4 | 21,9 | 8/2028 (+5,1) | ||||
8 | 30. | 10/2026 | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 1 066 | 4 | 3 | 13,0 | 10/2028 (+3,5) | |||||
9 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 11,3 km | 13 886 - 21 743 | 3 433 - 3 421 | 1 | 1 | 25,0 | 5/2029 (+5,1) | ||||
9 úsekov |
96,3 km |
2 - 4 |
2 435 mil. € |
76,9 km |
6 412 - 21 743 | 2,7 |
3,2 |
4/2028 - 6/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku