dátum |
plánovaný
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
pôvodný zmluvný termín
| |||||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | 12 387 - 17 316 | 109 - 210 | 2 | 3 | 12/2019 | 4/2026 | |||||
2 | 6. | 7/2023 | R2 | 6,8 km | 4 | 11 764 - 50 895 | 169 - 482 | 3 | 3 | 11/2021 | 7/2026 | |||||
3 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 8 140 - 13 204 | 76 - 172 | 3 | 3 | 4/2027 | 2/2031 | |||||
4 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 5 587 | 54 | 5 | 4 | 11/2026 | 2/2031 | |||||
5 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 42 774 - 54 519 | . . . | 266 - 354 | 3 | 2 | 3/2027 | 9/2032 | ||||
6 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 8 634 - 11 116 | 120 - 202 | 2 | 4 | 5/2027 | 3/2031 | |||||
7 | 41. | 9/2028 | R2 | 11,5 km | 2 | 7 793 | 82 | 2 | 4 | 11/2027 | 9/2031 | |||||
8 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 2 552 - 2 737 | 21 - 33 | 4 | 3 | 9/2027 | 11/2031 | |||||
9 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 9 492 - 10 279 | 112 - 134 | 3 | 2 | 12/2027 | 11/2030 | |||||
91,5 km |
2 - 6 |
2 552 - 54 519 | 3,0 |
3,1 |
4/2026 - 9/2032 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku