dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
1 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | 227 mil. € | 4 | 4 | 4/2029 (+4,1) | ||||||
2 | 7/2016 | R7 | 17,4 km | 4 | 8 544 - 13 236 | 2 | 3 | 7/2020 (+0,0) | 7/2020 (0,0) | ||||||
3 | 7/2016 | R7 | 8,4 km | 4 | 13 102 - 19 993 | 1 | 1 | 7/2020 (–1,0) | 7/2020 (0,0) | ||||||
4 | 12. | 7/2024 | R3 | 6,5 km | 2 | 70 mil. € | 6 706 - 9 733 | 2 | 2 | 7/2026 (+2,7) | |||||
5 | 6/2014 | D1 | 13,5 km | 4 | 555 mil. € | 22 691 - 32 334 | 1 | 2 | 2024 (+4,0) | ||||||
6 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | 161 mil. € | 6 403 - 9 478 | 4 | 5 | 5/2029 (+3,5) | |||||
7 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 224 mil. € | 10 140 - 11 010 | 3 | 5 | 12/2029 (+2,8) | |||||
8 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 785 mil. € | 8 140 - 13 204 | 3 | 3 | 2/2031 (+6,9) | |||||
8 úsekov |
110,7 km |
2 - 4 |
2 022 mil. € |
6 403 - 32 334 | 2,5 |
3,1 |
7/2020 - 2/2031 |
7/2020 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku