plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
13 úsekov |
119,4 km |
2 - 4 |
2 872 mil. € |
2 552 - 32 334 | 3,1 |
3,3 |
|||||||
1 | ![]() | D1 | 13,5 km | 4 | 555 mil. € | 22 691 - 32 334 | 1 | 2 | |||||
2 | ![]() | R4 | 8,2 km | 2 | 94 mil. € | 4 001 | 3 | 3 | |||||
3 | ![]() | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | ||||||
4 | ![]() | R3 | 8,3 km | 2 | 199 mil. € | 5 550 - 9 787 | 2 | 3 | |||||
5 | ![]() | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 1/2023 | ||||
6 | ![]() | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | 4 | 9/2022 | ||||
7 | ![]() | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 3 | 4 | 2/2023 | ||||
8 | ![]() | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 4 | |||||
9 | ![]() | R2 | 10,6 km | 2 | 125 mil. € | 6 412 - 8 112 | 4 | 4 | |||||
10 | ![]() | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 4 | 3 | |||||
11 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | ||||||
12 | ![]() | R4 | 7,9 km | 2 | 129 mil. € | 2 552 - 2 737 | 4 | 3 | |||||
13 | ![]() | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | ||||||
13 úsekov |
119,4 km |
2 - 4 |
2 872 mil. € |
2 552 - 32 334 | 3,1 |
3,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku