dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||
27 úsekov |
236,3 km |
2 - 8 |
5 823 mil. € |
2,4 |
2,7 |
||||||
1 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | |||
2 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 2 | 2 | |||
3 | 3/2020 | ![]() | R2 | 9,1 km | 4 | 267 mil. € | 3 | 4 | |||
4 | 1. | 10/2021 | ![]() | R4 | 14,3 km | 4 | 202 mil. € | 2 | 1 | ||
5 | 3. | 3/2022 | ![]() | D1 | 3,5 km | 8 | 149 mil. € | 1 | 1 | ||
6 | 4. | 9/2022 | ![]() | R4 | 10,2 km | 4 | 299 mil. € | 1 | 3 | ||
7 | 5. | 4/2023 | ![]() | R1 | 8,1 km | 4 | 173 mil. € | 2 | 3 | ||
8 | 6. | 7/2023 | ![]() | R2 | 6,8 km | 4 | 171 mil. € | 3 | 3 | ||
9 | 7. | 2/2024 | ![]() | D1 | 13,5 km | 4 | 1 235 mil. € | 1 | 1 | ||
10 | 8. - 9. | 3/2024 | ![]() | R2 | 6,2 km | 2 | 105 mil. € | 2 | 2 | ||
11 | 8. - 9. | 3/2024 | ![]() | R7 | 9,4 km | 4 | 191 mil. € | 4 | 5 | ||
12 | 10. | 4/2024 | ![]() | D1 | 3,8 km | 2 | 57 mil. € | 3 | 5 | ||
13 | 11. | 6/2024 | ![]() | R1 | 2,7 km | 4 | 155 mil. € | 4 | 3 | ||
14 | 12. | 7/2024 | ![]() | R3 | 6,5 km | 2 | 70 mil. € | 2 | 2 | ||
15 | 13. | 8/2024 | ![]() | R2 | 8,3 km | 2 | 169 mil. € | 2 | 2 | ||
16 | 14. - 15. | 10/2024 | ![]() | R7 | 23,5 km | 2 | 227 mil. € | 4 | 4 | ||
17 | 14. - 15. | 10/2024 | ![]() | R7 | 14,3 km | 2 | 172 mil. € | 4 | 4 | ||
18 | 16. - 17. | 12/2024 | ![]() | R7 | 8,4 km | 4 | 161 mil. € | 4 | 5 | ||
19 | 16. - 17. | 12/2024 | ![]() | R2 | 14,1 km | 2 | 272 mil. € | 3 | 2 | ||
20 | 18. | 4/2025 | ![]() | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | ||
21 | 19. | 6/2025 | ![]() | R4 | 8,2 km | 2 | 94 mil. € | 3 | 3 | ||
22 | 25. | 1/2026 | ![]() | D3 | 10,8 km | 4 | 309 mil. € | 2 | 4 | ||
23 | 27. | 5/2026 | ![]() | D3 | 11,2 km | 4 | 410 mil. € | 1 | 1 | ||
24 | 31. | 11/2026 | ![]() | D3 | 4,0 km | 4 | 179 mil. € | 1 | 2 | ||
25 | 34. - 36. | 6/2027 | ![]() | D1 | 10,6 km | 8 | 234 mil. € | 2 | 1 | ||
26 | 50. - 52. | 5/2030 | ![]() | R4 | 8,0 km | 2 | 133 mil. € | 4 | 3 | ||
27 | 71. - 78. | po 2040 | ![]() | R5 | 1,7 km | 2 | 54 mil. € | 3 | 4 | ||
27 úsekov |
236,3 km |
2 - 8 |
5 823 mil. € |
2,4 |
2,7 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku