plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
12 úsekov |
100,5 km |
2 - 4 |
2 379 mil. € |
2 552 - 16 268 | 3,3 |
3,4 |
6/2026 - 6/2033 |
|||||||
1 | R1 | 2,7 km | 4 | 155 mil. € | 16 268 | 4 | 3 | 10/2010 | 6/2026 (+3,5) | |||||
2 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 5/2007 | 10/2028 (+4,1) | ||||||
3 | R3 | 8,3 km | 2 | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 5/2007 | 10/2028 (+4,1) | |||||
4 | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 10/2005 | 10/2028 (+3,2) | |||||
5 | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | 4 | 10/2005 | 10/2028 (+4,2) | |||||
6 | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 3 | 4 | 10/2005 | 12/2028 (+4,3) | |||||
7 | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 1/2008 | 4/2028 (+4,8) | |||||
8 | R2 | 10,6 km | 2 | 125 mil. € | 6 412 - 8 112 | 4 | 4 | 10/2005 | 8/2028 (+5,1) | |||||
9 | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 4 | 3 | 10/2010 | 10/2028 (+3,5) | |||||
10 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 3/2022 | 6/2033 (+3,3) | ||||||
11 | R4 | 7,9 km | 2 | 129 mil. € | 2 552 - 2 737 | 4 | 3 | 10/2016 | 11/2031 (+4,8) | |||||
12 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 10/2014 | 2/2033 (+4,5) | ||||||
12 úsekov |
100,5 km |
2 - 4 |
2 379 mil. € |
2 552 - 16 268 | 3,3 |
3,4 |
6/2026 - 6/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku