dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 1.3.2012 | |||||
2 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 11,5 min. | 2 | 2 | 1.6.2017 | ||||
3 | 5. | 4/2023 | ![]() | R1 | 8,1 km | 4 | 173 mil. € | 2 | 3 | 09/2019 | ||||
4 | 6. | 7/2023 | ![]() | R2 | 6,8 km | 4 | 171 mil. € | 3 | 3 | 11/2013 | ||||
5 | 27. | 5/2026 | ![]() | D3 | 11,2 km | 4 | 410 mil. € | 13,0 min. | 1 | 1 | 1.1.2010 | |||
6 | 50. - 52. | 5/2030 | ![]() | R4 | 8,0 km | 2 | 133 mil. € | 8,0 min. | 4 | 3 | nezačaté | |||
7 | 50. - 52. | 5/2030 | ![]() | R4 | 7,5 km | 2 | 124 mil. € | 8,0 min. | 3 | 3 | nezačaté | |||
8 | 50. - 52. | 5/2030 | ![]() | R4 | 6,0 km | 2 | 101 mil. € | 5,0 min. | 4 | 3 | nezačaté | |||
9 | 53. - 54. | 7/2030 | ![]() | R6 | 11,2 km | 2 | 182 mil. € | 4 | 3 | nezačaté | ||||
10 | 53. - 54. | 7/2030 | ![]() | R6 | 11,3 km | 2 | 222 mil. € | 4 | 3 | nezačaté | ||||
10 úsekov |
87,9 km |
2 - 4 |
1 837 mil. € |
45,5 min. |
2,8 |
2,7 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku