dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 1 606 m | 112 mil. € | 8 634 - 11 116 | 120 - 202 | 2 | 4 | ||||
2 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 4 710 m | 129 mil. € | 2 552 - 2 737 | 21 - 33 | 4 | 3 | ||||
3 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 1 965 m | 176 mil. € | 5 189 - 6 389 | 49 - 72 | 5 | 5 | ||||
4 | 46. | 3/2029 | D1 | 7,3 km | 4 | 660 m | 321 mil. € | 10 359 | 51 | 3 | 3 | ||||
5 | 47. | 7/2029 | R2 | 14,0 km | 2 | 891 m | 117 mil. € | 5 809 - 8 826 | 56 - 84 | 5 | 4 | ||||
6 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 1 074 m | 93 mil. € | 6 452 - 10 032 | 69 - 107 | 5 | 5 | ||||
7 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 2 993 m | 133 mil. € | 5 814 - 7 518 | 59 - 68 | 4 | 3 | ||||
8 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 1 963 m | 124 mil. € | 3 769 - 3 897 | 42 - 55 | 3 | 3 | ||||
9 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 1 216 m | 101 mil. € | 3 782 - 6 302 | 12 - 96 | 4 | 3 | ||||
10 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 1 456 m | 191 mil. € | 14 233 - 18 874 | 35 - 248 | 3 | 3 | ||||
102,1 km |
2 - 4 |
18 533 m |
1 498 mil. € |
2 552 - 18 874 | 3,8 |
3,6 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku