dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
11 úsekov |
103,3 km |
2 - 8 |
1 655 mil. € |
66,9 km |
3,4 |
3,1 |
||||||||
1 | 3/2021 | R3 | 4,4 km | 2 | R3 sever (Orava) | 70 mil. € | 5,4 km | 2 | 2 | |||||
2 | 1. | 10/2021 | R4 | 14,3 km | 4 | R2 východ, R4 juh | 202 mil. € | 2 | 1 | |||||
3 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | D1 západ | 234 mil. € | 2 | 1 | |||||
4 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | R4 sever | 116 mil. € | 6,4 km | 2 | 3 | ||||
5 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | R4 sever | 122 mil. € | 7,0 km | 2 | 2 | ||||
6 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R2 východ | 176 mil. € | 17,0 km | 5 | 5 | ||||
7 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D4 sever | 133 mil. € | 5 | 5 | |||||
8 | 46. | 3/2029 | D1 | 7,3 km | 4 | D1 sever | 321 mil. € | 7,3 km | 3 | 3 | ||||
9 | 47. | 7/2029 | R2 | 14,0 km | 2 | R2 východ | 117 mil. € | 14,0 km | 5 | 4 | ||||
10 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R2 východ | 93 mil. € | 9,8 km | 5 | 5 | ||||
11 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | R3 stred (Turiec) | 71 mil. € | 4 | 3 | |||||
11 úsekov |
103,3 km |
2 - 8 |
1 655 mil. € |
66,9 km |
3,4 |
3,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku