dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||
15 úsekov |
141,1 km |
4 - 6 |
4 346 mil. € |
1,2 |
1,9 |
7/2020 - 5/2033 | ||||||
1 | 12/2013 | ![]() | D1 | 14,9 km | 4 | 341 mil. € | 1 | 1 | 2023 (+1,0) | |||
2 | 7/2016 | ![]() | D4 | 4,4 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | ||||
3 | 7/2016 | ![]() | D4 | 22,6 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | ||||
4 | 7/2016 | ![]() | R7 | 8,4 km | 4 | 1 | 1 | 7/2020 (–1,0) | ||||
5 | 55. - 56. | 5/2031 | ![]() | R1 | 11,5 km | 4 | 406 mil. € | 4 | 4 | 5/2033 (+10,2) | ||
6 | 6/2014 | ![]() | D1 | 13,5 km | 4 | 555 mil. € | 1 | 2 | 2024 (+4,0) | |||
7 | 31. | 11/2026 | ![]() | D3 | 4,0 km | 4 | 179 mil. € | 1 | 2 | 11/2030 (+6,4) | ||
8 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 2023 (+2,0) | |||
9 | 4. | 9/2022 | ![]() | R4 | 10,2 km | 4 | 299 mil. € | 1 | 3 | 1/2027 (+4,8) | ||
10 | 6/2017 | ![]() | D1 | 7,9 km | 4 | 434 mil. € | 1 | 2 | 7/2021 (0,0) | |||
11 | 7/2016 | ![]() | R7 | 6,4 km | 4 - 6 | 1 | 1 | 10/2021 (+0,3) | ||||
12 | 12/2017 | ![]() | D1 | 2,6 km | 4 | 39 mil. € | 1 | 1 | 2021 (+2,2) | |||
13 | 7. | 2/2024 | ![]() | D1 | 13,5 km | 4 | 1 235 mil. € | 1 | 1 | 12/2030 (+4,5) | ||
14 | 12/2016 | ![]() | D3 | 5,7 km | 4 | 269 mil. € | 1 | 2 | 2021 (+0,5) | |||
15 | 27. | 5/2026 | ![]() | D3 | 11,2 km | 4 | 410 mil. € | 1 | 1 | 5/2029 (+5,1) | ||
15 úsekov |
141,1 km |
4 - 6 |
4 346 mil. € |
1,2 |
1,9 |
7/2020 - 5/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku