dátum |
plánovaný
|
odhad NDS
|
3,5 - 12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 6/2017 | D1 | 7,9 km | 4 | D 26,5/100 | 0 | 434 mil. € | 19 072 - 21 988 | 456 - 660 | 1 | 2 | 10/2021 | ||||
2 | 12/2017 | D1 | 2,6 km | 4 | R 22,5/80 | 39 mil. € | 14 624 | 343 | 1 | 1 | 1/2021 (0,0) | |||||
3 | 13. | 8/2024 | R2 | 8,3 km | 2 | R 22,5/100, plánované v 1/2-profile | 169 mil. € | 5 277 - 6 250 | 175 - 206 | 2 | 2 | |||||
4 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 73 mil. € | 5 587 | 178 | 5 | 4 | |||||
5 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 | 176 mil. € | 5 189 - 6 389 | 153 - 173 | 5 | 5 | ||||
6 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | D 26,5/100 | 133 mil. € | 5 | 5 | |||||||
7 | 46. | 3/2029 | D1 | 7,3 km | 4 | 26,5/100 | 321 mil. € | 10 359 | 541 | 3 | 3 | |||||
8 | 47. | 7/2029 | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | 1 | 117 mil. € | 5 809 - 8 826 | 226 - 259 | 5 | 4 | ||||
9 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 6 452 - 10 032 | 212 - 272 | 5 | 5 | |||||
10 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | R 24,5/120(100), plánované v 1/2-profile | 71 mil. € | 5 441 - 8 427 | 196 - 287 | 4 | 3 | |||||
87,1 km |
2 - 4 |
2 |
1 625 mil. € |
5 189 - 21 988 | 3,6 |
3,4 |
1/2021 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku