dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 192 mil. € | 6 207 - 8 525 | 2 | 2 | |||||
2 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | ||||||
3 | 12. | 7/2024 | R3 | 6,5 km | 2 | 70 mil. € | 6 706 - 9 733 | 2 | 2 | |||||
4 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 4 | |||||
5 | 6/2017 | D1 | 7,9 km | 4 | 434 mil. € | 19 072 - 21 988 | 1 | 2 | 10/2021 | |||||
6 | 12/2017 | D1 | 2,6 km | 4 | 39 mil. € | 14 624 | 1 | 1 | 1/2021 (0,0) | |||||
7 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | ||||||
8 | 30. | 10/2026 | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 4 | 3 | |||||
8 úsekov |
103,9 km |
2 - 4 |
1 814 mil. € |
5 762 - 21 988 | 2,4 |
2,3 |
1/2021 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku