plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | D1 | 7,9 km | 4 | 434 mil. € | 19 072 - 21 988 | 15 504 - 18 825 | 1 | 2 | 3/2009 | 10/2021 | |||
2 | D1 | 2,6 km | 4 | 39 mil. € | 14 624 | 12 446 | 1 | 1 | 2/2006 | 1/2021 (0,0) | |||
3 | R1 | 14,9 km | 4 | 785 mil. € | 8 140 - 13 204 | 6 735 - 10 692 | 3 | 3 | 3/2024 | ||||
4 | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 4 388 | 5 | 4 | 7/2020 | ||||
5 | R2 | 9,6 km | 2 | 112 mil. € | 8 634 - 11 116 | 6 810 - 9 018 | 2 | 4 | 7/2011 | ||||
6 | R2 | 11,5 km | 2 | 235 mil. € | 7 793 | 5 879 | 2 | 4 | 11/2010 | ||||
7 | R4 | 7,9 km | 2 | 129 mil. € | 2 552 - 2 737 | 1 041 - 1 549 | 4 | 3 | 2/2023 | ||||
8 | R3 | 5,0 km | 2 | 63 mil. € | 9 492 - 10 279 | 8 049 - 8 636 | 3 | 2 | 5/2024 | ||||
67,2 km |
2 - 4 |
1 869 mil. € |
2 552 - 21 988 | 2,6 |
2,9 |
1/2021 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku