✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
# |
dátum |
plánovaný
|
odhad NDS
|
stavebné práce
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||
128,4 km |
2 - 8 |
2 902 mil. € |
575,7 mil. € |
1,4 |
1,1 |
11/2015 - 10/2021 | |||||||
1 | 12/2013 | ![]() | D1 | 14,9 km | 4 | 341 mil. € | 227,3 mil. € | 1 | 1 | ||||
2 | 12/2013 | ![]() | R2 | 10,4 km | 4 | 178,0 mil. € | 1 | 1 | 11/2015 | ||||
3 | 1/2014 | ![]() | R2 | 9,6 km | 2 | 88,2 mil. € | 2 | 1 | 10/2016 | ||||
4 | 8/2014 | ![]() | R2 | 7,9 km | 4 | 88 mil. € | 82,3 mil. € | 1 | 1 | 5/2017 | |||
5 | 7/2016 | ![]() | R7 | 8,4 km | 4 | 1 | 1 | 7/2020 (0,0) | |||||
6 | 7/2016 | ![]() | R7 | 6,4 km | 4 - 6 | 1 | 1 | 10/2021 | |||||
7 | 12/2017 | ![]() | D1 | 2,6 km | 4 | 39 mil. € | 1 | 1 | 22,0 | 1/2021 (0,0) | |||
8 | 1. | 10/2021 | ![]() | R4 | 14,3 km | 4 | 202 mil. € | 2 | 1 | 14,4 | |||
9 | 3. | 3/2022 | ![]() | D1 | 3,5 km | 8 | 149 mil. € | 1 | 1 | 13,8 | |||
10 | 7. | 2/2024 | ![]() | D1 | 13,5 km | 4 | 1 235 mil. € | 1 | 1 | 24,0 | |||
11 | 18. | 4/2025 | ![]() | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 20,2 | |||
12 | 27. | 5/2026 | ![]() | D3 | 11,2 km | 4 | 410 mil. € | 1 | 1 | 25,0 | |||
13 | 34. - 36. | 6/2027 | ![]() | D1 | 10,6 km | 8 | 234 mil. € | 2 | 1 | 13,8 | |||
14 | 57. - 58. | 6/2031 | ![]() | R3 | 14,0 km | 4 | 191 mil. € | 3 | 3 | 14,3 | |||
128,4 km |
2 - 8 |
2 902 mil. € |
575,7 mil. € |
1,4 |
1,1 |
11/2015 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku