dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||
21 úsekov |
327,7 km |
2 - 6 |
5 535 mil. € |
1 698 - 93 344 | 2,0 |
2,4 |
12/2019 - 8/2037 | ||||||||
1 | 12/2013 | ![]() | D1 | 14,9 km | 4 | 341 mil. € | 12 491 - 24 900 | 926 - 1 852 | 1 | 1 | 2023 (+1,0) | ||||
2 | 1/2014 | ![]() | D1 | 11,3 km | 4 | 517 mil. € | 23 579 - 28 413 | 1 675 - 2 070 | 2 | 3 | 2021 (+2,1) | ||||
3 | 6/2014 | ![]() | D1 | 13,5 km | 4 | 555 mil. € | 22 691 - 32 334 | 1 254 - 2 069 | 1 | 2 | 2024 (+4,0) | ||||
4 | 7/2016 | ![]() | R7 | 17,4 km | 4 | 8 544 - 13 236 | 609 - 806 | 2 | 3 | 7/2020 (+0,0) | |||||
5 | 7/2016 | ![]() | D4 | 4,4 km | 4 - 6 | 1 | 2 | 11/2021 (+0,4) | |||||||
6 | 7/2016 | ![]() | D4 | 22,6 km | 4 - 6 | 32 336 - 93 344 | . . . | 1 679 - 8 658 | 1 | 2 | 11/2021 (+0,4) | ||||
7 | 7/2016 | ![]() | R7 | 8,4 km | 4 | 13 102 - 19 993 | 676 - 881 | 1 | 1 | 7/2020 (–1,0) | |||||
8 | 7/2016 | ![]() | R7 | 6,4 km | 4 - 6 | 27 633 - 44 493 | . . . | 1 073 - 2 257 | 1 | 1 | 10/2021 (+0,3) | ||||
9 | 11/2016 | ![]() | D1 | 14,4 km | 4 | 241 mil. € | 3 166 - 11 562 | 191 - 682 | 2 | 2 | 12/2019 | ||||
10 | 12/2016 | ![]() | D3 | 5,7 km | 4 | 269 mil. € | 11 465 - 18 743 | 741 - 995 | 1 | 2 | 2021 (+0,5) | ||||
11 | 6/2017 | ![]() | D1 | 7,9 km | 4 | 434 mil. € | 19 072 - 21 988 | 1 228 - 1 350 | 1 | 2 | 7/2021 (0,0) | ||||
12 | 12/2017 | ![]() | D1 | 2,6 km | 4 | 39 mil. € | 14 624 | 800 | 1 | 1 | 2021 (+2,2) | ||||
13 | 8. - 9. | 3/2024 | ![]() | R2 | 6,2 km | 2 | 105 mil. € | 5 304 | 462 | 2 | 2 | 3/2026 (+4,7) | |||
14 | 57. - 58. | 6/2031 | ![]() | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 333 - 812 | 3 | 5 | 6/2036 (+2,3) | |||
15 | 64. - 68. | 8/2033 | ![]() | D1 | 12,6 km | 4 | 418 mil. € | 9 503 - 9 802 | 678 - 730 | 3 | 3 | 8/2036 (+7,9) | |||
16 | 64. - 68. | 8/2033 | ![]() | D1 | 18,2 km | 4 | 192 mil. € | 6 207 - 8 525 | 404 - 665 | 2 | 2 | 8/2036 (+7,9) | |||
17 | 64. - 68. | 8/2033 | ![]() | D1 | 15,8 km | 4 | 139 mil. € | 4 033 - 8 369 | 217 - 330 | 4 | 3 | 8/2036 (+7,7) | |||
18 | 64. - 68. | 8/2033 | ![]() | D1 | 12,1 km | 4 | 162 mil. € | 10 444 - 14 783 | 659 - 820 | 3 | 3 | 8/2036 (+7,7) | |||
19 | 64. - 68. | 8/2033 | ![]() | D1 | 15,5 km | 4 | 136 mil. € | 1 698 - 6 812 | 70 - 361 | 4 | 3 | 8/2036 (+7,7) | |||
20 | 69. - 70. | 8/2034 | ![]() | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | |||||
21 | 69. - 70. | 8/2034 | ![]() | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 525 - 852 | 4 | 4 | 8/2037 (+5,9) | |||
21 úsekov |
327,7 km |
2 - 6 |
5 535 mil. € |
1 698 - 93 344 | 2,0 |
2,4 |
12/2019 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku