✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
# |
dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 64. - 68. | 8/2033 | D1 | 15,8 km | 4 | 139 mil. € | 16,0 min. | 4 033 - 8 369 | 4 | 3 | 11/2031 | |||||
2 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 11,5 min. | 9 007 - 9 998 | 2 | 2 | 12/2018 | ||||||
3 | 1/2014 | D1 | 11,3 km | 4 | 517 mil. € | 13,0 min. | 23 579 - 28 413 | 2 | 3 | 11/2008 | 1/2021 (0,0) | |||||
4 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | 191 mil. € | 7,0 min. | 6 428 - 9 084 | 4 | 5 | ||||||
5 | 6/2017 | D1 | 7,9 km | 4 | 434 mil. € | 11,0 min. | 19 072 - 21 988 | 1 | 2 | 6/2015 | 10/2021 | |||||
6 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 7,0 min. | 10 334 - 11 542 | 2 | 2 | 7/2012 | ||||||
7 | 7/2019 | R4 | 4,3 km | 4 | 179 mil. € | 15 837 - 18 098 | 1 | 3 | 1/2017 | |||||||
8 | 12/2017 | D1 | 2,6 km | 4 | 39 mil. € | 14 624 | 1 | 1 | 11/2015 | 1/2021 (0,0) | ||||||
8 úsekov |
69,2 km |
2 - 4 |
1 711 mil. € |
65,5 min. |
4 033 - 28 413 | 2,1 |
2,6 |
1/2021 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku