dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 1/2014 | D1 | 11,3 km | 4 | 3 585 m | 517 mil. € | 13,0 min. | 23 579 - 28 413 | 2 | 3 | 1/2021 (0,0) | |||||
2 | 6/2017 | D1 | 7,9 km | 4 | 1 863 m | 434 mil. € | 11,0 min. | 19 072 - 21 988 | 1 | 2 | 10/2021 | |||||
3 | 12/2017 | D1 | 2,6 km | 4 | 76 m | 39 mil. € | 14 624 | 1 | 1 | 1/2021 (0,0) | ||||||
4 | 7/2019 | R4 | 4,3 km | 4 | 884 m | 179 mil. € | 15 837 - 18 098 | 1 | 3 | |||||||
5 | 8/2019 | R2 | 13,5 km | 4 | 1 631 m | 142 mil. € | 11,5 min. | 9 007 - 9 998 | 2 | 2 | ||||||
6 | 3/2021 | R3 | 4,4 km | 2 | 1 568 m | 70 mil. € | 7,0 min. | 10 334 - 11 542 | 2 | 2 | ||||||
7 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | 2 006 m | 227 mil. € | 4 | 4 | |||||||
8 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 397 m | 73 mil. € | 5,0 min. | 5 587 | 5 | 4 | |||||
9 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | ||||||
9 úsekov |
83,8 km |
2 - 6 |
12 010 m |
1 771 mil. € |
47,5 min. |
5 587 - 32 968 | 2,6 |
2,9 |
1/2021 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku