dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | R 22,5/100, plánované v 1/2-profile | 105 mil. € | 5 304 | 2 | 2 | 10/2005 | ||||||
2 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | R 11,5/100 (80) | 182 mil. € | 9,2 % (Púchov - hranica SR/ČR) | 7 234 | 4 | 3 | 7/2020 | |||||
3 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | R 11,5/100 (80) | 222 mil. € | 9,2 % (Púchov - hranica SR/ČR) | 2 561 - 5 054 | 4 | 3 | 7/2020 | |||||
4 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | R 24,5/100 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 11/2024 | ||||||
5 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 611 mil. € | -1,3 % (Zvolen-Šahy) | 3 247 - 11 434 | 4 | 4 | 1/2020 | |||||
5 úsekov |
142,0 km |
2 - 4 |
2 139 mil. € |
2 561 - 11 477 | 3,4 |
3,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku