dátum |
plánovaný
|
odhad NDS
|
3,5 - 12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 12. | 7/2024 | R3 | 6,5 km | 22,4 % | 2 | 70 mil. € | 6 706 - 9 733 | 1 568 - 1 801 | 204 - 321 | 2 | 2 | |||||
2 | 50. - 52. | 5/2030 | R4 | 8,0 km | 36,3 % | 2 | 133 mil. € | 5 814 - 7 518 | 733 - 1 326 | 127 - 169 | 4 | 3 | |||||
3 | 53. - 54. | 7/2030 | R6 | 11,2 km | 26,4 % | 2 | 182 mil. € | 7 234 | 1 058 | 142 | 4 | 3 | |||||
4 | 50. - 52. | 5/2030 | R4 | 7,5 km | 24,3 % | 2 | 124 mil. € | 3 769 - 3 897 | 1 529 - 1 844 | 95 - 115 | 3 | 3 | |||||
5 | 50. - 52. | 5/2030 | R4 | 6,0 km | 17,0 % | 2 | 101 mil. € | 3 782 - 6 302 | 1 697 - 2 149 | 102 - 192 | 4 | 3 | |||||
6 | 42. - 43. | 11/2028 | R4 | 7,9 km | 57,5 % | 2 | 129 mil. € | 2 552 - 2 737 | 1 003 - 1 696 | 77 - 169 | 4 | 3 | |||||
7 | 53. - 54. | 7/2030 | R6 | 11,3 km | 30,1 % | 2 | 222 mil. € | 2 561 - 5 054 | 573 - 803 | 105 - 136 | 4 | 3 | |||||
7 úsekov |
58,4 km |
31,0 % |
2 |
961 mil. € |
2 552 - 9 733 | 3,6 |
2,9 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku