dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 12/2013 | D1 | 14,9 km | 4 | Hubová, Likavka, Ivachnová | 341 mil. € | 12 491 - 24 900 | 1 | 1 | 3/2005 | 12/2010 | |||||
2 | 3/2020 | R2 | 9,1 km | 4 | Kriváň | 267 mil. € | 8 780 - 11 203 | 3 | 4 | 6/2011 | ||||||
3 | 6/2014 | D1 | 13,5 km | 4 | Lietavská Lúčka | 555 mil. € | 22 691 - 32 334 | 1 | 2 | 12/2007 | ||||||
4 | 8/2019 | R2 | 13,5 km | 4 | Mýtna | 142 mil. € | 9 007 - 9 998 | 2 | 2 | 6/2011 | 12/2017 | |||||
5 | 7/2019 | R4 | 4,3 km | 4 | Prešov - sever | 179 mil. € | 15 837 - 18 098 | 1 | 3 | 9/2015 | 12/2017 | |||||
6 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | Zemné | 227 mil. € | 4 | 4 | 11/2021 | ||||||
7 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | Plešivec | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2024 | 11/2027 | ||||
8 | 3/2021 | R3 | 4,4 km | 2 | Nižná,
Nižná - sever | 70 mil. € | 10 334 - 11 542 | 2 | 2 | 9/2009 | 11/2016 | |||||
101,3 km |
2 - 4 |
1 957 mil. € |
5 189 - 32 334 | 2,4 |
2,9 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku