1 | 6/2014 | ![]() | D1 | 13,5 km | 4 | 555 mil. € | 22 691 - 32 334 | 1 254 - 2 069 | 1 | 2 | ||||||
2 | 6/2017 | ![]() | D1 | 7,9 km | 4 | 434 mil. € | 19 072 - 21 988 | 1 228 - 1 350 | 1 | 2 | 10/2021 | |||||
3 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 15 837 - 18 098 | 917 - 967 | 1 | 3 | 17,5 | |||||
4 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 9 007 - 9 998 | 831 - 943 | 2 | 2 | 16,0 | |||||
5 | 3/2021 | ![]() | R3 | 4,4 km | 2 | 70 mil. € | 10 334 - 11 542 | 639 - 801 | 2 | 2 | 27,0 | |||||
6 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 28,0 | ||||||
7 | 48. - 49. | 9/2029 | ![]() | R3 | 7,9 km | 2 | 71 mil. € | 5 441 - 8 427 | 423 - 703 | 4 | 3 | 14,3 | ||||
8 | 64. - 68. | 8/2033 | ![]() | D1 | 12,1 km | 4 | 162 mil. € | 10 444 - 14 783 | 659 - 820 | 3 | 3 | 24,0 | ||||
8 úsekov |
68,4 km |
2 - 4 |
1 690 mil. € |
5 441 - 32 334 | 2,0 |
2,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku