dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 6/2014 | ![]() | D1 | 13,5 km | 4 | 1 | 555 mil. € | 22 691 - 32 334 | 133 - 458 | 1 | 2 | |||||
2 | 6/2017 | ![]() | D1 | 7,9 km | 4 | 0 | 434 mil. € | 19 072 - 21 988 | 220 - 372 | 1 | 2 | 10/2021 | ||||
3 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 15 837 - 18 098 | 213 - 312 | 1 | 3 | 1.3.2012 | |||||
4 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 9 007 - 9 998 | 51 - 106 | 2 | 2 | 1.6.2017 | |||||
5 | 3/2021 | ![]() | R3 | 4,4 km | 2 | 1 | 70 mil. € | 10 334 - 11 542 | 230 - 281 | 2 | 2 | 07/2010 | ||||
6 | 48. - 49. | 9/2029 | ![]() | R3 | 7,9 km | 2 | 71 mil. € | 5 441 - 8 427 | 30 - 78 | 4 | 3 | nezačaté | ||||
7 | 62. - 63. | 10/2032 | ![]() | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | nezačaté | ||||||
8 | 64. - 68. | 8/2033 | ![]() | D1 | 18,2 km | 4 | 192 mil. € | 6 207 - 8 525 | 94 - 185 | 2 | 2 | nezačaté | ||||
76,5 km |
2 - 6 |
2 |
1 750 mil. € |
5 441 - 32 334 | 2,3 |
2,6 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku