dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||
1 | 6/2014 | ![]() | D1 | 13,5 km | 4 | 555 mil. € | 1 | 2 | 4/2009 | 2024 (+4,0) | ||||
2 | 6/2017 | ![]() | D1 | 7,9 km | 4 | 434 mil. € | 1 | 2 | 6/2015 | 7/2021 (0,0) | 10/2021 | |||
3 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 1/2017 | 2023 (+2,0) | ||||
4 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 2 | 2 | 12/2018 | 2021 (+1,1) | ||||
5 | 3/2021 | ![]() | R3 | 4,4 km | 2 | 70 mil. € | 2 | 2 | 7/2012 | 8/2022 (+2,2) | ||||
6 | 48. - 49. | 9/2029 | ![]() | R3 | 7,9 km | 2 | 71 mil. € | 4 | 3 | 5/2028 | 9/2032 (+4,1) | |||
7 | 64. - 68. | 8/2033 | ![]() | D1 | 18,2 km | 4 | 192 mil. € | 2 | 2 | 11/2031 | 8/2036 (+7,9) | |||
7 úsekov |
69,6 km |
2 - 4 |
1 643 mil. € |
1,9 |
2,3 |
7/2021 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku