dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 6/2014 | ![]() | D1 | 13,5 km | 4 | D1 sever | 555 mil. € | 22 691 - 32 334 | 133 - 458 | 1 | 2 | ||||
2 | 6/2017 | ![]() | D1 | 7,9 km | 4 | D1 východ | 434 mil. € | 19 072 - 21 988 | 220 - 372 | 1 | 2 | 10/2021 | |||
3 | 7/2019 | ![]() | R4 | 4,3 km | 4 | R4 stred | 179 mil. € | 15 837 - 18 098 | 213 - 312 | 1 | 3 | ||||
4 | 8/2019 | ![]() | R2 | 13,5 km | 4 | R2 stred | 142 mil. € | 9 007 - 9 998 | 51 - 106 | 2 | 2 | ||||
5 | 3/2021 | ![]() | R3 | 4,4 km | 2 | R3 sever (Orava) | 70 mil. € | 10 334 - 11 542 | 230 - 281 | 2 | 2 | ||||
6 | 16. - 17. | 12/2024 | ![]() | R7 | 8,4 km | 4 | R7 západ | 161 mil. € | 6 403 - 9 478 | 32 - 113 | 4 | 5 | |||
7 | 28. - 29. | 8/2026 | ![]() | R4 | 4,0 km | 4 | R4 stred | 105 mil. € | 14 625 | 181 | 2 | 2 | |||
8 | 42. - 43. | 11/2028 | ![]() | R3 | 5,0 km | 2 | R3 juh | 63 mil. € | 9 492 - 10 279 | 112 - 134 | 3 | 2 | |||
9 | 50. - 52. | 5/2030 | ![]() | R4 | 6,0 km | 2 | R4 sever | 101 mil. € | 3 782 - 6 302 | 12 - 96 | 4 | 3 | |||
67,0 km |
2 - 4 |
1 810 mil. € |
3 782 - 32 334 | 2,2 |
2,6 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku