dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 6/2014 | D1 | 13,5 km | 4 | Lietavská Lúčka | 555 mil. € | 22 691 - 32 334 | 1 | 2 | |||||
2 | 7/2016 | D4 | 4,4 km | 4 - 6 | Čierna voda, Rača | 1 | 2 | |||||||
3 | 7/2016 | D4 | 22,6 km | 4 - 6 | Jarovce, Rusovce, Ketelec, Rovinka, Ivanka západ, Ivanka sever | 32 336 - 93 344 | . . . | 1 | 2 | |||||
4 | 7/2016 | R7 | 6,4 km | 4 - 6 | Prievoz | 27 633 - 44 493 | . . . | 1 | 1 | 10/2021 | ||||
5 | 1. | 10/2021 | R4 | 14,3 km | 4 | Košice-juh, Krásna, Hrašovík | 202 mil. € | 10 088 - 50 895 | 2 | 1 | ||||
6 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 4 | |||||
7 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | ||||||
8 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | Okrúhle | 122 mil. € | 3 407 - 3 769 | 2 | 2 | ||||
9 | 47. | 7/2029 | R2 | 14,0 km | 2 | Turňa nad Bodvou | 117 mil. € | 5 809 - 8 826 | 5 | 4 | ||||
10 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | Dargov | 418 mil. € | 9 503 - 9 802 | 3 | 3 | ||||
128,0 km |
2 - 6 |
2 398 mil. € |
3 407 - 93 344 | 2,3 |
2,5 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku