dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 6/2014 | ![]() | D1 | 13,5 km | 4 | 1 | 555 mil. € | 1 | 2 | |||||
2 | 3/2020 | ![]() | R2 | 9,1 km | 4 | 267 mil. € | 3 | 4 | 11/2004 | 6/2018 | ||||
3 | 1. | 10/2021 | ![]() | R4 | 14,3 km | 4 | 1 | 202 mil. € | 2 | 1 | 6/2014 | 12/2018 | ||
4 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 5/2004 | 12/2017 | ||||
5 | 6. | 7/2023 | ![]() | R2 | 6,8 km | 4 | 0 | 171 mil. € | 3 | 3 | 6/2014 | 7/2022 | ||
6 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 2 | 2 | 11/2004 | 2/2018 | ||||
7 | 19. | 6/2025 | ![]() | R4 | 8,2 km | 2 | 94 mil. € | 3 | 3 | 1/2000 | 6/2024 | |||
8 | 3/2021 | ![]() | R3 | 4,4 km | 2 | 1 | 70 mil. € | 2 | 2 | 8/2006 | 8/2017 | |||
9 | 7/2016 | ![]() | D4 | 4,4 km | 4 - 6 | 1 | 2 | |||||||
10 | 7/2016 | ![]() | D4 | 22,6 km | 4 - 6 | 1 | 2 | |||||||
101,1 km |
2 - 6 |
3 |
1 681 mil. € |
1,9 |
2,4 |
8/2017 - 6/2024 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku