dátum |
plánovaný
|
jednostranné / obojstranné
|
odhad NDS
|
rok
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||
1 | 6/2014 | ![]() | D1 | 13,5 km | 4 | Turie | 555 mil. € | 9,5 min. | 2030 | 1 | 2 | |||
2 | 7/2016 | ![]() | D4 | 4,4 km | 4 - 6 | 1 | 2 | |||||||
3 | 7/2016 | ![]() | D4 | 22,6 km | 4 - 6 | 1 | 2 | |||||||
4 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 2030 | 1 | 3 | |||||
5 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 9,5 min. | 2031 | 2 | 2 | ||||
6 | 3/2020 | ![]() | R2 | 9,1 km | 4 | 267 mil. € | 6,5 min. | 2030 | 3 | 4 | ||||
7 | 3/2021 | ![]() | R3 | 4,4 km | 2 | Tvrdošín | 70 mil. € | 3,8 min. | 2030 | 2 | 2 | |||
8 | 1. | 10/2021 | ![]() | R4 | 14,3 km | 4 | Valaliky | 202 mil. € | 2025 | 2 | 1 | |||
9 | 6. | 7/2023 | ![]() | R2 | 6,8 km | 4 | 171 mil. € | 2035 | 3 | 3 | ||||
10 | 14. - 15. | 10/2024 | ![]() | R7 | 14,3 km | 2 | Zemné | 172 mil. € | 2030 | 4 | 4 | |||
107,2 km |
2 - 6 |
1 759 mil. € |
29,3 min. |
2,0 |
2,5 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku