dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 6/2014 | ![]() | D1 | 13,5 km | 4 | 555 mil. € | 1 | 2 | 6/2014 | |||||
2 | 7/2016 | ![]() | D4 | 4,4 km | 4 - 6 | 1 | 2 | 7/2016 | ||||||
3 | 7/2016 | ![]() | D4 | 22,6 km | 4 - 6 | 1 | 2 | 7/2016 | ||||||
4 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 7/2019 | |||||
5 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 2 | 2 | 8/2019 | |||||
6 | 3/2020 | ![]() | R2 | 9,1 km | 4 | 267 mil. € | 3 | 4 | 3/2020 | |||||
7 | 3/2021 | ![]() | R3 | 4,4 km | 2 | 70 mil. € | 2 | 2 | 3/2021 | |||||
8 | 1. | 10/2021 | ![]() | R4 | 14,3 km | 4 | 202 mil. € | 2 | 1 | 10/2021 | 1 | |||
9 | 6. | 7/2023 | ![]() | R2 | 6,8 km | 4 | 171 mil. € | 3 | 3 | 7/2023 | 6 | |||
10 | 59. | 7/2031 | ![]() | R2 | 17,5 km | 4 | 287 mil. € | 2 | 2 | 7/2031 | 58 | |||
110,4 km |
2 - 6 |
1 874 mil. € |
1,8 |
2,3 |
6/2014 - 7/2031 |
1 - 58 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku