dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 6/2014 | D1 | 13,5 km | 4 | 555 mil. € | 10 992 | 22 691 - 32 334 | 1 | 2 | ||||||
2 | 7/2016 | D4 | 4,4 km | 4 - 6 | 1 | 2 | |||||||||
3 | 7/2016 | D4 | 22,6 km | 4 - 6 | 32 336 - 93 344 | . . . | 1 | 2 | |||||||
4 | 7/2016 | R7 | 6,4 km | 4 - 6 | 27 633 - 44 493 | . . . | 1 | 1 | 10/2021 | ||||||
5 | 1. | 10/2021 | R4 | 14,3 km | 4 | 202 mil. € | 3 530 | 10 088 - 50 895 | 2 | 1 | |||||
6 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 1 992 | 5 587 | 5 | 4 | |||||
7 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 974 | 5 814 - 7 518 | 4 | 3 | |||||
8 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 1 951 | 3 782 - 6 302 | 4 | 3 | |||||
9 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 3 174 | 14 233 - 18 874 | 3 | 3 | |||||
9 úsekov |
97,0 km |
2 - 6 |
1 256 mil. € |
3 782 - 93 344 | 2,4 |
2,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku