dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||
1 | 37. - 38. | 2/2028 | ![]() | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 5 | 4 | 2/2031 (+4,1) | |||
2 | 50. - 52. | 5/2030 | ![]() | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | |||
3 | 6/2014 | ![]() | D1 | 13,5 km | 4 | 555 mil. € | 22 691 - 32 334 | 1 | 2 | 2024 (+4,0) | ||||
4 | 69. - 70. | 8/2034 | ![]() | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | |||
5 | 10. | 4/2024 | ![]() | D1 | 3,8 km | 2 | 57 mil. € | 10 312 | 3 | 5 | 4/2027 (+4,1) | |||
6 | 71. - 78. | po 2040 | ![]() | R7 | 71,3 km | 2 | 553 mil. € | 1 065 - 4 239 | 5 | 5 | po 2040 (0,0) | |||
6 úsekov |
153,4 km |
2 - 4 |
2 033 mil. € |
1 065 - 32 334 | 3,7 |
3,8 |
7/2024 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku