dátum |
plánovaný
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||||
1 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 8 195 | 5 814 - 7 518 | 59 - 68 | 4 | 3 | 5/2033 (+6,1) | 91. | |||||
2 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 7 637 | 3 769 - 3 897 | 42 - 55 | 3 | 3 | 5/2033 (+6,1) | 45. | |||||
3 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 8 391 | 3 782 - 6 302 | 12 - 96 | 4 | 3 | 5/2033 (+6,1) | 80. | |||||
4 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 5 938 - 12 956 | 7 234 | 66 | 4 | 3 | 7/2033 (+4,3) | 17. | |||||
5 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 1 942 - 3 996 | 2 561 - 5 054 | 18 - 42 | 4 | 3 | 7/2033 (+4,3) | 14. | |||||
6 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | 1 303 - 10 541 | 3 247 - 11 434 | 45 - 182 | 4 | 4 | po 2040 (+13,9) | 11. | |||||
6 úsekov |
102,5 km |
2 |
2 561 - 11 434 | 3,8 |
3,2 |
5/2033 - po 2040 |
11. - 91. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku