dátum |
plánovaný
|
odhad NDS
|
1 - optimálne,
5 - neprimerané |
prebratie
|
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | 12. | 7/2024 | R3 | 6,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 70 mil. € | 6 706 - 9 733 | 2 | 5/2015 | 7/2026 (+2,7) | |||||
2 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 133 mil. € | 5 814 - 7 518 | 3 | 12/2014 | 5/2033 (+6,1) | |||||
3 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | R 11,5/100 (80) | 182 mil. € | 7 234 | 3 | 2/2016 | 7/2033 (+4,3) | |||||
4 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | R 24,5/100, plánované v 1/2-profile | 124 mil. € | 3 769 - 3 897 | 3 | 12/2014 | 5/2033 (+6,1) | |||||
5 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | R 24,5/100, plánované v 1/2-profile | 101 mil. € | 3 782 - 6 302 | 3 | 12/2014 | 5/2033 (+6,1) | |||||
6 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | R 11,5/100 (80) | 222 mil. € | 2 561 - 5 054 | 3 | 2/2016 | 7/2033 (+4,3) | |||||
6 úsekov |
50,5 km |
2 |
832 mil. € |
2 561 - 9 733 | 2,8 |
7/2026 - 7/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku