dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||||
1 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 42 774 - 54 519 | . . . | 3 862 - 4 344 | 3 | 2 | 9/2032 (+5,6) | ||||
2 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 427 - 551 | 4 | 3 | 7/2033 (+4,3) | |||||
3 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 7 234 | 632 | 4 | 3 | 7/2033 (+4,3) | |||||
4 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 2,6 min. | 5 814 - 7 518 | 349 - 902 | 4 | 3 | 5/2033 (+6,1) | ||||
5 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3,6 min. | 3 769 - 3 897 | 1 289 - 1 580 | 3 | 3 | 5/2033 (+6,1) | ||||
6 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 1,2 min. | 3 782 - 6 302 | 1 492 - 1 737 | 4 | 3 | 5/2033 (+6,1) | ||||
6 úsekov |
63,9 km |
2 - 6 |
1 083 mil. € |
7,4 min. |
2 561 - 54 519 | 3,7 |
2,8 |
9/2032 - 7/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku