dátum |
plánovaný
|
odhad NDS
|
na aktuálne plánovaný počet jazdných pruhov
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 67 mil. € | 2,5 min. | 2 | 2 | 6,0 | ||||||
2 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 118 mil. € | 1,6 min. | 5 814 - 7 518 | 4 | 3 | 4,0 | |||||
3 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 161 mil. € | 7 234 | 4 | 3 | 3,0 | ||||||
4 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 110 mil. € | 2,8 min. | 3 769 - 3 897 | 3 | 3 | 4,0 | |||||
5 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 87 mil. € | 0,8 min. | 3 782 - 6 302 | 4 | 3 | 4,0 | |||||
6 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 199 mil. € | 2 561 - 5 054 | 4 | 3 | 3,0 | ||||||
6 úsekov |
48,9 km |
2 |
839 mil. € |
742 mil. € |
7,6 min. |
2 561 - 7 518 | 3,5 |
2,8 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku