dátum |
plánovaný
|
odhad NDS
|
pozemky
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | Lipníky | 105 mil. € | 8,5 mil. € | 2,5 min. | 14 625 | 2 | 2 | ||||
2 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | Kuková | 133 mil. € | 6,0 mil. € | 6,4 min. | 5 814 - 7 518 | 4 | 3 | ||||
3 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | Stročín | 101 mil. € | 6,1 mil. € | 4,2 min. | 3 782 - 6 302 | 4 | 3 | ||||
4 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | Púchov západ,
Púchov východ,
Dolné Kočkovce | 182 mil. € | 10,0 mil. € | 7 234 | 4 | 3 | |||||
5 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | Mestečko | 222 mil. € | 11,0 mil. € | 2 561 - 5 054 | 4 | 3 | |||||
6 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | Stupava | 107 mil. € | 3,9 mil. € | 5 | 5 | ||||||
47,3 km |
2 - 6 |
849 mil. € |
45,5 mil. € |
13,1 min. |
2 561 - 14 625 | 3,8 |
3,2 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku