dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
135,6 km |
2 - 4 |
4 040 mil. € |
2,1 |
2,4 |
|||||||||
1 | 12/2013 | ![]() | D1 | 14,9 km | 4 | 341 mil. € | 1 | 1 | |||||
2 | 6/2017 | ![]() | D1 | 7,9 km | 4 | 434 mil. € | 1 | 2 | 2/2001 | 10/2021 | |||
3 | 7/2019 | ![]() | R4 | 4,3 km | 4 | 179 mil. € | 1 | 3 | 5/2004 | ||||
4 | 8/2019 | ![]() | R2 | 13,5 km | 4 | 142 mil. € | 2 | 2 | 11/2004 | ||||
5 | 3/2020 | ![]() | R2 | 9,1 km | 4 | 267 mil. € | 3 | 4 | 11/2004 | ||||
6 | 3/2021 | ![]() | R3 | 4,4 km | 2 | 70 mil. € | 2 | 2 | 8/2006 | ||||
7 | 1. | 10/2021 | ![]() | R4 | 14,3 km | 4 | 202 mil. € | 2 | 1 | 6/2014 | |||
8 | 4. | 9/2022 | ![]() | R4 | 10,2 km | 4 | 299 mil. € | 1 | 3 | 5/2004 | |||
9 | 5. | 4/2023 | ![]() | R1 | 8,1 km | 4 | 173 mil. € | 2 | 3 | 4/2010 | |||
10 | 6. | 7/2023 | ![]() | R2 | 6,8 km | 4 | 171 mil. € | 3 | 3 | 6/2014 | |||
11 | 7. | 2/2024 | ![]() | D1 | 13,5 km | 4 | 1 235 mil. € | 1 | 1 | ||||
12 | 8. - 9. | 3/2024 | ![]() | R7 | 9,4 km | 4 | 191 mil. € | 4 | 5 | 12/2011 | |||
13 | 16. - 17. | 12/2024 | ![]() | R2 | 14,1 km | 2 | 272 mil. € | 3 | 2 | 9/2009 | |||
14 | 42. - 43. | 11/2028 | ![]() | R3 | 5,0 km | 2 | 63 mil. € | 3 | 2 | 11/2018 | |||
135,6 km |
2 - 4 |
4 040 mil. € |
2,1 |
2,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku