dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 7. | 2/2024 | D1 | 13,5 km | 4 | 1 235 mil. € | 13 676 - 21 949 | 1 | 1 | 4/2008 | 6/2023 | ||||||
2 | 13. | 8/2024 | R2 | 8,3 km | 2 | 169 mil. € | 5 277 - 6 250 | 2 | 2 | 3/2020 | 12/2023 | ||||||
3 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 105 mil. € | 5,9 % (Kapušany - V. Komárnik) | 14 625 | 2 | 2 | 12/2023 | 8/2025 | |||||
4 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5,75 % (Tornaľa - Včeláre) | 5 189 - 6 389 | 5 | 5 | 1/2026 | 2/2028 | |||||
5 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 6/2028 | ||||||||
6 | 46. | 3/2029 | D1 | 7,3 km | 4 | 321 mil. € | 10 359 | 3 | 3 | 6/2024 | 7/2028 | ||||||
7 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5,85 % (Včeláre - Šaca) | 5 809 - 8 826 | 5 | 4 | 7/2026 | 7/2028 | |||||
8 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 5,75 % (Tornaľa - Včeláre) | 6 452 - 10 032 | 5 | 5 | 9/2026 | 9/2028 | |||||
9 | 48. - 49. | 9/2029 | R3 | 7,9 km | 2 | 71 mil. € | 5,8 % (Martin - Horná Štubňa) | 5 441 - 8 427 | 4 | 3 | 2/2027 | 1/2029 | |||||
9 úsekov |
86,4 km |
2 - 4 |
2 419 mil. € |
5 189 - 21 949 | 3,6 |
3,3 |
6/2023 - 1/2029 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku