dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||
11 úsekov |
122,3 km |
2 - 4 |
2 766 mil. € |
3,2 |
3,2 |
10/2028 - 6/2034 |
|||||||
1 | 7. | 2/2024 | D1 | 13,5 km | 4 | 1 235 mil. € | 1 | 1 | 12/2030 (+4,5) | ||||
2 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 2 | 2 | 10/2028 (+3,2) | ||||
3 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 1 | 2 | 11/2030 (+6,4) | ||||
4 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 112 mil. € | 2 | 4 | 3/2031 (+5,9) | ||||
5 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 129 mil. € | 4 | 3 | 11/2031 (+4,8) | ||||
6 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 | 5 | 2/2032 (+4,9) | ||||
7 | 47. | 7/2029 | R2 | 14,0 km | 2 | 117 mil. € | 5 | 4 | 7/2032 (+5,3) | ||||
8 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | 93 mil. € | 5 | 5 | 9/2032 (+5,6) | ||||
9 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 4 | 3 | 5/2033 (+6,1) | ||||
10 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3 | 3 | 5/2033 (+6,1) | ||||
11 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 3 | 3 | 6/2034 (+7,0) | ||||
11 úsekov |
122,3 km |
2 - 4 |
2 766 mil. € |
3,2 |
3,2 |
10/2028 - 6/2034 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku