dátum |
plánovaný
|
odhad NDS
|
3,5 - 12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
13 úsekov |
155,6 km |
2 - 4 |
3 092 mil. € |
2 156 - 21 949 | 3,5 |
3,3 |
12/2029 - po 2040 |
|||||||||
1 | 7. | 2/2024 | ![]() | D1 | 13,5 km | 4 | 1 235 mil. € | 13 676 - 21 949 | 422 - 799 | 1 | 1 | 12/2030 (+4,5) | ||||
2 | 16. - 17. | 12/2024 | ![]() | R2 | 14,1 km | 2 | 272 mil. € | 5 792 - 7 064 | 192 - 224 | 3 | 2 | 12/2029 (+5,4) | ||||
3 | 31. | 11/2026 | ![]() | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 588 | 1 | 2 | 11/2030 (+6,4) | ||||
4 | 39. - 40. | 3/2028 | ![]() | R2 | 9,6 km | 2 | 112 mil. € | 8 634 - 11 116 | 240 - 422 | 2 | 4 | 3/2031 (+5,9) | ||||
5 | 42. - 43. | 11/2028 | ![]() | R4 | 7,9 km | 2 | 129 mil. € | 2 552 - 2 737 | 77 - 169 | 4 | 3 | 11/2031 (+4,8) | ||||
6 | 44. - 45. | 2/2029 | ![]() | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 153 - 173 | 5 | 5 | 2/2032 (+4,9) | ||||
7 | 47. | 7/2029 | ![]() | R2 | 14,0 km | 2 | 117 mil. € | 5 809 - 8 826 | 226 - 259 | 5 | 4 | 7/2032 (+5,3) | ||||
8 | 48. - 49. | 9/2029 | ![]() | R2 | 9,8 km | 2 | 93 mil. € | 6 452 - 10 032 | 212 - 272 | 5 | 5 | 9/2032 (+5,6) | ||||
9 | 50. - 52. | 5/2030 | ![]() | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 127 - 169 | 4 | 3 | 5/2033 (+6,1) | ||||
10 | 50. - 52. | 5/2030 | ![]() | R4 | 7,5 km | 2 | 124 mil. € | 3 769 - 3 897 | 95 - 115 | 3 | 3 | 5/2033 (+6,1) | ||||
11 | 50. - 52. | 5/2030 | ![]() | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 102 - 192 | 4 | 3 | 5/2033 (+6,1) | ||||
12 | 57. - 58. | 6/2031 | ![]() | R3 | 14,0 km | 4 | 191 mil. € | 14 233 - 18 874 | 489 - 601 | 3 | 3 | 6/2034 (+7,0) | ||||
13 | 71. - 78. | po 2040 | ![]() | R7 | 29,2 km | 2 | 230 mil. € | 2 156 - 6 890 | 90 - 156 | 5 | 5 | po 2040 (0,0) | ||||
13 úsekov |
155,6 km |
2 - 4 |
3 092 mil. € |
2 156 - 21 949 | 3,5 |
3,3 |
12/2029 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku