dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||
117,1 km |
2 - 6 |
1 803 mil. € |
1,8 |
2,5 |
10/2021 - 10/2021 | |||||
1 | 12/2013 | ![]() | 14,9 km | 4 | 341 mil. € | 1 | 1 | |||
2 | 7/2016 | ![]() | 4,4 km | 4 - 6 | 1 | 2 | ||||
3 | 7/2016 | ![]() | 22,6 km | 4 - 6 | 1 | 2 | ||||
4 | 7/2016 | ![]() | 6,4 km | 4 - 6 | 1 | 1 | 10/2021 | |||
5 | 6/2017 | ![]() | 7,9 km | 4 | 434 mil. € | 1 | 2 | 10/2021 | ||
6 | 7/2019 | ![]() | 4,3 km | 4 | 179 mil. € | 1 | 3 | |||
7 | 8/2019 | ![]() | 13,5 km | 4 | 142 mil. € | 2 | 2 | |||
8 | 3/2020 | ![]() | 9,1 km | 4 | 267 mil. € | 3 | 4 | |||
9 | 3/2021 | ![]() | 4,4 km | 2 | 70 mil. € | 2 | 2 | |||
10 | 14. - 15. | 10/2024 | ![]() | 23,5 km | 2 | 227 mil. € | 4 | 4 | ||
11 | 24. | 12/2025 | ![]() | 6,1 km | 4 | 143 mil. € | 3 | 4 | ||
117,1 km |
2 - 6 |
1 803 mil. € |
1,8 |
2,5 |
10/2021 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku