dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 12/2013 | D1 | 14,9 km | 4 | Hubová, Likavka, Ivachnová | 341 mil. € | 12 491 - 24 900 | 1 | 1 | |||||
2 | 12. | 7/2024 | R3 | 6,5 km | 2 | privádzač Krupina | 70 mil. € | 6 706 - 9 733 | 2 | 2 | ||||
3 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | Mliečany s II/507, Dolný Bar | 161 mil. € | 6 403 - 9 478 | 4 | 5 | ||||
4 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | Trenčianske Mitice | 277 mil. € | 9 654 - 12 079 | 2 | 2 | ||||
5 | 27. | 5/2026 | D3 | 11,2 km | 4 | Brodno, Kysucké Nové Mesto | 410 mil. € | 13 886 - 21 743 | 1 | 1 | ||||
6 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | ||||||
7 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | Kuková | 116 mil. € | 6 651 - 9 113 | 2 | 3 | ||||
76,0 km |
2 - 4 |
2 147 mil. € |
6 403 - 24 900 | 2,1 |
2,6 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku